Lećevica: renewed procurement, opening date uncertain
What is established
Media reports describe renewed phase-two procurement and continued delays; the estimate is not a contract, and trial operation in 2028 remains a projection.
Open questions
- Underlying current tender and award files.
- Certified phase-one expenditure.
- A binding current construction and operating schedule.
Money journey: what is documented
These stages do not prove that the same euro passed through every step. Grants and contracts may be part of a budget, not additional spending.
Unknown is not zero.
Every amount and its period
Budget / estimate3 amounts
Excludes VAT. Secondary report of an announcement, not a contract award or payments. Phase two only; publication date does not establish the cost period.
Excludes VAT; historical estimate, not a contract or final cost. Component of the then-project; the announced 2023 deadline does not prove the actual expenditure period.
Originally: 146.000.000,00 HRK · Nominal conversion at HRK 7.5345 per euro; not inflation-adjusted.
Earlier frame Regionalni centar čistog okoliša d.o.o.Overlaps phase one. Not comparable to the newer phase-two estimate without reconciling scope and VAT; not verified 2022 spending.
Originally: 611.419.690,00 HRK · Nominal conversion at HRK 7.5345 per euro; not inflation-adjusted.
Earlier frame Regionalni centar čistog okoliša d.o.o.What the money tells us
January 2026 media reporting gives €70.19 million plus VAT as the phase-two procurement estimate, not an award or amount paid. The utility’s July 2022 announcement gives HRK 146,000,000.00 excluding VAT for phase-one design/build procurement and a then-estimated whole-project value of HRK 611,419,690.00. These figures concern different phases, scopes and estimation dates. Without reconciling scope, VAT and funding eligibility, they cannot be directly compared or added as a financial loss. No final project expenditure is established here.
Figures have different purposes and periods. They should not automatically be added together or treated as losses.
Read the full explanation
In July 2022, Regionalni centar čistog okoliša explained construction in two phases through inflation, procurement and EU-funding eligibility constraints. Media reports from January and February 2026 describe renewed phase-two procurement and continued delays. The projection of trial operation in summer 2028 depends on procurement and commencement assumptions; it is not a binding opening date. Underlying current tender and award files were not retrieved. Lećevica is separate from Karepovac remediation, although both matter for regional waste capacity.
Institutions and companies mentioned in the sources
Being mentioned does not establish guilt, ownership or responsibility.
- Regionalni centar čistog okoliša d.o.o.
- Splitsko-dalmatinska županija
- Fond za zaštitu okoliša i energetsku učinkovitost
- JASPERS
- Ministarstvo zaštite okoliša i zelene tranzicije
- Grad Split
Check the sources 3
Open the documents on their publishers’ websites. Links lead to the public originals, not a private archive.